Paving to begin Monday in city

Work on the 2013 city street milling and paving program is to begin Monday. Weather permitting, work is to begin on Coe Street, south of Jefferson street, and on Circular Street east of Washington Street.

Sections of the following streets are also included in this year’s program:

West Market Street, east of Hopewell Avenue.

Wentz Street, east of Pizza Hut.

Riverside Drive, near the viaduct and Industrial Avenue.

Sycamore Street, between South Monroe and Circular streets.

Jefferson, between Main and Madison streets.

Washington between Hudson and Noble streets.

Traffic is to be maintained with flaggers, but there may be some delays. Motorists are advised to avoid the work areas if possible.

Work is to continue until complete, an estimated 7-10 days.